Projects→Bafq, Yazd
Current Project • Turnkey EPC

Bafq 48 MW Industrial Power Plant

An ongoing turnkey EPC project based on fourteen 3.4 MW Jenbacher J620 generating units. The present record covers survey control, site preparation and foundation excavation.

Plant capacityApprox. 48 MW
Generating units14
Capacity per unit3.4 MW
Engine manufacturerJenbacher
Engine modelJ620
LocationBafq, Yazd
Delivery modelEPC • Turnkey
StatusIn progress
Present Workfront

Civil works and foundation preparation

The current record documents activities completed or underway at the photographed stage of the project.

01

Survey & level control

Existing conditions and working elevations checked against the access road, adjacent substation and surrounding site.

02

Site preparation

The production-hall workfront graded and prepared for excavation and machinery access.

03

Foundation excavation

Generator and structural foundation positions set out and excavated across the production-hall area.

04

Foundation logistics

Excavator mobilization, soil removal and delivery of purchased reinforcing steel coordinated with the civil-work programme.

Project Progress

From survey control to excavated foundations

A concise selection of clear, project-specific photographs. Other similar or lower-value images remain in the internal archive.

01

Existing-condition survey and level control

Survey of the site and adjacent conditions, including the access road, nearby electrical substation and relevant elevation changes.

02

Earthmoving and soil removal

Excavation and loading undertaken together to keep the civil-work area accessible and ready for the next operation.

03

Foundation setting out

Generator and structural foundation boundaries transferred to the site from the verified survey control.

04

Production-hall excavation

Excavation progressing across the production-hall area and the locations assigned to generating-unit foundations.

05

Excavated foundation layout

Overall view of the excavated trenches before dimensional, positional and elevation checks for the next foundation activities.

Project Detail

Current published project record

The record will continue to develop as construction and equipment installation advance.

Project overview

The approximately 48 MW plant comprises fourteen project-rated 3.4 MW Jenbacher J620 generating units.

Current scope

Turnkey EPC delivery is underway. The present stage includes surveying, level control, site grading, production-hall excavation and generator-foundation preparation.